The biggest decisions about cost are made early, often before the drawings are detailed enough to measure. That is when an early cost estimate is most useful.

How an early estimate works

Instead of pricing every item, an early estimate prices the building by major element: substructure, structure, envelope, internal finishes, services and external works. Rates are drawn from comparable projects and adjusted for your quality level and site.

Why use one?

  • Test affordability. Find out early whether the concept fits the budget.
  • Compare options. See how changes in size, shape or finishes affect cost.
  • Guide design decisions. Know which elements drive cost.
  • Support early conversations. With lenders, partners or advisers.

How accurate is it?

An early estimate is a guide and carries a wider allowance than a measured estimate. As the design develops, it is refined and then replaced by a detailed estimate.

Early versus detailed estimates

StageEstimate typeBased on
Concept / feasibilityCost plan by elementAreas, sketch plans, benchmarks
Developed designCost plan or measuredDeveloped drawings
Construction documentsDetailed estimateMeasured quantities and priced items